Construction of the main structure of Taihu Tunnel is in full swing
Release time:2018-10-10 Browse:
 

  

At noon on October 9, the construction of Taihu Tunnel of the Southern Suzhou-Wuxi-Changzhou Expressway ushered in an important node. The first floor of the buried section of the under-lake tunnel at Nanquan construction site began to be poured, and was expected to be completed after 15 hours, meaning that the construction of the main structure of the under-lake section of Taihu Tunnel was in full swing.

 

It is reported that at present, there are four compartments in Nanquan construction site that have completed the cofferdam. Mashan construction site, facing Nanquan construction site from the lake, is also progressing in an orderly manner. The Southern Suzhou-Wuxi-Changzhou Expressway is scheduled to complete the construction of the main structure of Taihu Tunnel in December, 2020, and will be fully opened to traffic at the end of December, 2021.

 